Breaker control scheme for rebuilding networks containing distributed generation following system disturbances

Wen T Shang, Miles A Redfern, R O'Gorman

Research output: Chapter in Book/Report/Conference proceedingChapter

Abstract

Following a system disturbance when there is a loss of grid, under current UK practice, all distributed generators have to be disconnected automatically from the network in less than 500 msecs and remain disconnected until the normal grid supply is restored. They can then be resynchronised and reconnected to the grid supply. However, these distributed generators offer the potential to maintain supplies to consumers during loss of grid, an opportunity which is currently being lost. This paper explores new techniques to enable distributed generators in distributed networks to provide continuity of supply during power system disturbances which result in loss of grid, and thereby enhances the quality of supply to consumers.
Original languageEnglish
Title of host publicationProceedings of the 11th International Scientific Conference Electric Power Engineering 2010
PublisherBrno Univ Techol
Pages113-118
Number of pages6
ISBN (Print)978-80-214-4094-4
Publication statusPublished - 2010
Event11th International Scientific Conference on Electric Power Engineering 2010 - Brno, Czech Republic
Duration: 4 May 20106 May 2010

Conference

Conference11th International Scientific Conference on Electric Power Engineering 2010
CountryCzech Republic
CityBrno
Period4/05/106/05/10

Fingerprint

Distributed power generation
Electric power systems

Cite this

Shang, W. T., Redfern, M. A., & O'Gorman, R. (2010). Breaker control scheme for rebuilding networks containing distributed generation following system disturbances. In Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010 (pp. 113-118). Brno Univ Techol.

Breaker control scheme for rebuilding networks containing distributed generation following system disturbances. / Shang, Wen T; Redfern, Miles A; O'Gorman, R.

Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010. Brno Univ Techol, 2010. p. 113-118.

Research output: Chapter in Book/Report/Conference proceedingChapter

Shang, WT, Redfern, MA & O'Gorman, R 2010, Breaker control scheme for rebuilding networks containing distributed generation following system disturbances. in Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010. Brno Univ Techol, pp. 113-118, 11th International Scientific Conference on Electric Power Engineering 2010, Brno, Czech Republic, 4/05/10.
Shang WT, Redfern MA, O'Gorman R. Breaker control scheme for rebuilding networks containing distributed generation following system disturbances. In Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010. Brno Univ Techol. 2010. p. 113-118
Shang, Wen T ; Redfern, Miles A ; O'Gorman, R. / Breaker control scheme for rebuilding networks containing distributed generation following system disturbances. Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010. Brno Univ Techol, 2010. pp. 113-118
@inbook{395bee921e014722b859f173ff586a0d,
title = "Breaker control scheme for rebuilding networks containing distributed generation following system disturbances",
abstract = "Following a system disturbance when there is a loss of grid, under current UK practice, all distributed generators have to be disconnected automatically from the network in less than 500 msecs and remain disconnected until the normal grid supply is restored. They can then be resynchronised and reconnected to the grid supply. However, these distributed generators offer the potential to maintain supplies to consumers during loss of grid, an opportunity which is currently being lost. This paper explores new techniques to enable distributed generators in distributed networks to provide continuity of supply during power system disturbances which result in loss of grid, and thereby enhances the quality of supply to consumers.",
author = "Shang, {Wen T} and Redfern, {Miles A} and R O'Gorman",
year = "2010",
language = "English",
isbn = "978-80-214-4094-4",
pages = "113--118",
booktitle = "Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010",
publisher = "Brno Univ Techol",

}

TY - CHAP

T1 - Breaker control scheme for rebuilding networks containing distributed generation following system disturbances

AU - Shang, Wen T

AU - Redfern, Miles A

AU - O'Gorman, R

PY - 2010

Y1 - 2010

N2 - Following a system disturbance when there is a loss of grid, under current UK practice, all distributed generators have to be disconnected automatically from the network in less than 500 msecs and remain disconnected until the normal grid supply is restored. They can then be resynchronised and reconnected to the grid supply. However, these distributed generators offer the potential to maintain supplies to consumers during loss of grid, an opportunity which is currently being lost. This paper explores new techniques to enable distributed generators in distributed networks to provide continuity of supply during power system disturbances which result in loss of grid, and thereby enhances the quality of supply to consumers.

AB - Following a system disturbance when there is a loss of grid, under current UK practice, all distributed generators have to be disconnected automatically from the network in less than 500 msecs and remain disconnected until the normal grid supply is restored. They can then be resynchronised and reconnected to the grid supply. However, these distributed generators offer the potential to maintain supplies to consumers during loss of grid, an opportunity which is currently being lost. This paper explores new techniques to enable distributed generators in distributed networks to provide continuity of supply during power system disturbances which result in loss of grid, and thereby enhances the quality of supply to consumers.

M3 - Chapter

SN - 978-80-214-4094-4

SP - 113

EP - 118

BT - Proceedings of the 11th International Scientific Conference Electric Power Engineering 2010

PB - Brno Univ Techol

ER -